Machine Documentation and Acceptance Terms: What to Agree Before You Sign

Illustrative scene of a manual, a clipboard checklist and tray samples for documentation
Illustrative documentation review: a manual, a clipboard checklist and tray samples.

"It runs fine" is not acceptance. On a box forming machine order, acceptance should mean one thing: the machine meets criteria you agreed in advance, under test conditions you agreed in advance, with the result recorded and signed. This article covers the document package to request and the acceptance terms worth settling with your supplier before the order is signed.

What "acceptance" should mean in a machine order

Acceptance is the moment responsibility shifts: the machine is no longer "the supplier project" but part of your production. If that moment is defined by a verbal nod at the end of a commissioning day, every later dispute — about output, box quality or downtime — has no reference point to be judged against.

Agree on three things before the order is signed:

The criteria should trace back to your approved baseline: the approved box drawing and sample. Keep the drawing version number in the order file — every later check refers back to it.

The three parts of acceptance
PartWhat to agree
CriteriaWhat the machine must demonstrate, stated in measurable terms: boxes formed to the approved sample, dimensions within the tolerances on the approved drawing, sustained output under the agreed test conditions.
ConditionsWhich board, adhesive, operators and utilities the test will use, and for how long it will run.
EvidenceWho records the results, and what document both parties sign.

Agree the box drawing and sample baseline

FAT vs SAT: what each test proves

Buyers often treat factory and site testing as the same event with a different postcode. They prove different things, and a clear order uses both.

For both tests, record the same things: date, materials used, settings, output and quality results, deviations, and the signatures of both parties. Ask in advance what your supplier checks before shipment, and ask how the FAT report will be written and shared.

FAT vs SAT: what each test proves
PointFAT — Factory Acceptance TestSAT — Site Acceptance Test
Where and whenAt the supplier factory, usually before shipment.At your site, after installation.
What it provesThe machine is complete and correctly assembled: it forms boxes to your approved sample on your board, and supplier engineers can adjust and demonstrate it.Performance under your real conditions — the utilities, board and operators the machine will live with.
What it cannot proveHow the machine behaves on your power, your air and your materials, installed by your team.Whether the machine is sound if the site is not ready: a SAT run on a marginal air supply tests your compressor, not the machine.
Records to agreeThe box sample, board and test points, and how the FAT report will be written and shared.The same set of records, plus the signed SAT report.

Prepare the installation conditions first

See how Xunding handles quality checks

The document package to request

Machines arrive with documents in very different states of completeness, and "we will send everything" is not a document list. List the package in the contract, and check each item at handover:

Information on certifications sits on our certification page; ask there or through the contact page if you need documentation for a specific market. Agree in advance which documents are handed over on paper, which electronically, and in which languages — and record who at your site receives and files them.

Documents to list in the contract
DocumentWhat to check
Operation and maintenance manualsCovering settings, adjustments and routine tasks.
Electrical and layout drawingsThe versions actually used to build the machine.
Parameter and settings recordsFrom commissioning and the tests.
FAT reportAnd, later, the signed SAT report.
Spare parts listWith the wear parts identified.
Training recordWho was trained, on what, and when.
Approved box drawing and sample referenceThe baseline the machine was set to.

Review certification and machine documentation

Acceptance clauses worth agreeing on

This is not legal advice, and your contract team should review the wording. But from a technical standpoint, three clauses separate a smooth acceptance from an open-ended one:

Write these clauses against the test criteria, not as standalone boilerplate. A clause that says "accepted when criteria in Annex X are met" is stronger than one that says "accepted on successful operation", because it points at a document both parties already agreed.

Acceptance clauses to settle
ClauseWhat to agree
Deviation handlingHow failures found during testing are classified, the deadline for closing them, and whether the machine is accepted with open items or only after a retest.
Retest termsWho pays for a retest, and what happens if a retest is needed because site conditions, not the machine, caused the failure.
Acceptance and payment linkWhich payment stage, and which warranty start date, is triggered by the signed SAT report rather than by the shipping date.

FAQ: should final payment depend on acceptance?

Should final payment depend on acceptance?

Many buyers link the final payment stage — and the warranty start — to a signed acceptance report rather than to shipment. Suppliers who expect this arrangement can plan for it; suppliers who learn about it after the invoice is issued cannot.

When should I raise it?

While the order is being negotiated, and alongside the FAT/SAT plan and the document package above — so the paperwork and the payment schedule are agreed in the same conversation as the machine.

Take the lists from this article, mark which documents and clauses matter for your line, and send them before the order is signed.